Answer: The degree of influence that the investor has over the investee.
To report this investment within the company's financial statements, according to IFRS, they depend into two options:
- Stock control: An entity controls a business when it is exposed or has rights over earnings and has the ability to affect these results through its power in the business.
- Minority percentage: The acquirer recognizes in their books an uncontrolled participation and in this case, no decisive decisions can be made.
Answer:
711,300
Explanation:
Net cash generated from operating activities can be calculated by deducting and adding back the cash and non-cash items respectively from the net income for the year. Such as depreciation will be added back in net income due to it is a non-cash expense
Net Income 624,000
Depreciation and amortization 87,000
Decrease in accounts receivable 22,000
Increase in inventories (9,200)
Increase prepaid expenses (8,500)
Increase in salaries payable 10,000
Decrease in income taxes payable (14,000
)
Net cash generated from operating activities 711,300
Answer:
Charging Sales tax
Explanation:
Merchandising business is the kind of business, that buys or purchases the finished products and then resells them to the customers.
So, the merchandising business could act as a collection agency for the government through charging the sales tax. There is need to remit the government after collecting the tax and when it is done, the business will decrease the cash and the sales tax liability.
And it is the lability to the government until it is remitted by the business.
Answer:
$305,000
Explanation:
Net income is the amount of money available to a company after the deduction of expenses from revenue. It is calculated as;
Net income = Revenues - Expenses
Given that;
Revenues = $630,000
Expenses = $325,000
Net income = $630,000 - $325,000
Net income = $305,000
Therefore the net income reported by Blue Spruce Corp. For the year is $305,000
Answer:
A) Analogous Estimation
Explanation:
Analogous Estimation is the process of comparing past costs and expenses of projects to make estimations for the current projects. This is usually used when there is data limitation for accurate estimations on the current projects.
Parametric is where a unit rate is devised to calculate project costs comprising of several units.
Bottom up estimation deals with estimating smaller cost components and then using the sum of these components to make larger estimates.
Option D is based on rough estimates on the time and effort required for a project.
None of the other options thus take into account past work other than the analogous estimation technique.
Hope that helps.