Answer:
Quantity variance.
Explanation:
The difference between actual and standard cost caused by the difference between the actual quantity and the standard quantity is called the Quantity variance.
For instance, if Tony needs a standard quantity of 50 pounds of iron to construct a burglary, but only used 51 pounds, then the quantity variance is 1 pound of iron.
<em>Hence, the quantity variance is simply the difference between the actual quantity of materials that should be used and the quantity of materials that was used. </em>
<span>Joneen gave Sue a cartway claim to access her own property across a portion of Joneen's property. This type of easement allows an individual to access their property via another, privately owned parcel for the purposes of accessing landlocked property.</span>
Answer:
D: $259,000
Explanation:
The computation of the paying amount which borrower can pay for a property is shown below:
= Mortgage loan amount for borrow ÷ loan-to-value ratio
= $220,000 ÷ 85%
= $258,823.53
= $259,000 round off
We simply divide the mortgage loan by the loan to value ratio so that paying amount could arrive which borrower can pay for a property.
Answer:
B. One year from now, Stock X's price is expected to be higher than Stock Y's price.
Explanation:
Hope it helped...Please mark brainliest. Have a nice day!