Answer:
Financial
Explanation:
Financial management refers to managing an organization or program's resources to meet it's goals and objectives as quickly as possible by making use of resources to carry out planned activities. A financial management system is the approach employed by an organization to govern its income, expenses and assets with the sole purpose of attaining sustability.
Answer: The creditor will be able to recover $1,350
Explanation:
The amount that the creditor will be able to recover will be the contract price less the damages for the minor breach by the company.
In this case, the company finished all of the tasks except for the cleaning of the oven. Since this is minor with regards to the contract, the company will be seen to have performed its contract.
Since we are told the cost of finishing the job was 10% of the contract cost, this will be regarded as a minor breach, therefore, the owner of the condominium cannot avoid the payment of the price of the contract price. In this case, the creditor will be able to recover ($1500 - $150) = $1,350.
The second one is the best chance to be self employed at because logisticians require a degree and there is less call for them.
Answer:
30%
Explanation:
The computation of the profit margin is shown below:
Given that
Net income earned for the month of October = $3,000
And, the net sales for the month of October is $10,000
Based on the above information, the profit margin is
= Net income ÷ Net sales
= $3,000 ÷ $10,000
= 30%
By dividing the net income from the net sales we can get the profit margin and the same is to be considered
Answer:
22 days
Explanation:
number of activities : 3 ( A,B,C)
connected via : SS and FF combination. days lag on SS and F = 2
Durations : 5,10 and 3
A and B is connected by SS and there is a 2-day lag on the SS connection, this means that B will start 2 days after A have ended
i.e when T = 0 , B will start : 5 +2 = 7 days and end in 17 days
while B and C is connected by FF and there is also a 2-day lag on the FF connection, this means that C will start after B has ended and end in 2 days
i.e when B ends at 17 days ; C starts = 17 + 2 = 19 DAYS
hence the project will end in 19 + 3 = 22 days ( i.e when C ends )