<h3>Your answer is a Upward Trend.</h3>
The correct answer to your question is Upward Trend. A Upward Trend is a movement in a factanal asset when the overall direction is above or upward. There are also Downwards Trends, which is when the same thing happens but the trend goes down. For example, a chart keeps going up, 9, 11, 16, 25 etc. This is an upward trend. If it goes down that would be considered a downward trend.
Answer:
the value of the short forward contract is -0.49
Explanation:
the computation of the value of the short forward contract is shown below:
= (Delivery price - current forward price)× e^(risk free interest rate × no of months ÷ total number of months)
= ($42.25 - $42.75)× e^(-7.90% × 4÷12)
= -0.49
Hence, the value of the short forward contract is -0.49
Therefore the same should be considered
<h2>
10 workers would cause the marginal to exceed the marginal benefits.</h2>
Explanation:
- Let us understand the term "Marginal benefits".
- It is the additional amount that the consumer "willing to pay" for an additional goods or a service.
- In terms of producers, the marginal benefit is termed as marginal revenue.
- Here according to the situation given in the question as to how many workers to hire could be answered by the number 10.
- Marginal revenue always falls below marginal cost.
- It is the revenue that the organization receives for selling one additional unit.
Answer: CPM and PERT use different activity time estimates.
Explanation:
Program (Project) Management and Review Technique (PERT) is appropriate when the project time needed to complete different activities are unknown while the Critical Path Method or CPM is fitted for recurring projects in nature. PERT deals with activities that are not predictable but CPM deals with repetitive activities. PERT focuses/concentrates on time while CPM focuses on time-cost & trade-off. Also, PERT requires three-time estimate while CPM requires one-time estimate. PERT uses a probabilistic model and on the other hand, CPM uses a deterministic model. In PERT, a technique of planning and controlling time is used but CPM uses a technique to control cost and time.