Answer: 4/3 hours or 1 1/3 hours
Step-by-step explanation:
From the question, we are told that two mechanics, Martin and Gordon, are working on your car. Martin can complete the work in 4 hours, while Gordon can complete the work in 2 hours.
Since Martin can complete the work in 4 hours, that means in 1 hour, he will do 1/4 of the work.
Since Gordon can complete the work in 2 hours, that means in 1 hour, he'll do 1/2 of the job.
When they both work together, we will add their fraction of work done in one hour together. This will be:
= 1/4 + 1/2
= 3/4
This means that both of them will do 3/4 of the job in one hour. Then to get the time taken to get the whole job done, we divide 1 by 3/4. This will be:
= 1 ÷ 3/4
= 1 × 4/3
= 4/3 hours
= 1 hour 20 minutes.
In one
The answer to this question is 4x= y-4
Answer:
Thats easy C:
2 and 3 at the same time
Step-by-step explanation:
3x2=6 or if you dived 6/2=3
Also one thing when doing markup or profit(I think thats how you spell it if not im srry my spelling is very bad lol) you dived it
Have a good day :D
454.42, it’s the net about of the money before anything is deducted
(0,4)(2,-3)
slope = (-3 - 4) / (2 - 0) = -7/2