Answer:
B
Explanation:
First, a monopoly produce less than the socially efficient quantity because as the figure shows, the quantity produced is determined by the intersection between the marginal cost curve (MC) and the marginal revenue curve (MR) and not by the intersection between the MC and the demand. For instance, there is a deadweight loss (shown by the figure).
Second, equilibrium price is always higher than in a competitive market because is always higher than the MC. The price is determined by the equilibrium quantity (found before) and the demand. Also, there are barries to entry and so monopolist have always price control.
Answer and Explanation:
The computation of the amount is shown below:
a. For FOB destination
= Merchandise price - Returns and allowances - discount
= $6,700 - $1,750 - ($6,700 - $1,750 )× 2%
= $6,700 - $1,750 - $99
= $4,851
b. For FOB shipping point
= Merchandise price - Returns and allowances - discount + Freight In
= $3,300 - $1,200 - ($3,300 - $1,200) × 1% + $200
= $3,300 - $1,200 - $21 + $200
= $2,279
Answer: C. The security risks associated with combining USB drives and cell phones on a network
D. The risks associated with the large capacity of USB drives and their concealable nature
Explanation:
Based on the scenario that has been discussed in the question, the security administrator will instructs the marketing staff not to supply the USB pens based on the security risks that are associated with combining USB drives and cell phones on a network.
Another reason is due to the risks that are associated with the large capacity of USB drives and their concealable nature.
Since the client has been victimized by social engineering attacks that led to a loss of sensitive data in the past, they'll be extra careful this time around.
Answer:
It's c.
Explanation:
Program Evaluation and Review Technique (PERT) is a method used in program management. It analyzes the time required to complete each task in a project and so tries to determine the minimum time to complete a project. It was developed by the US Navy in 1957.
In PERT analysis:
- there are 3 time estimates for every activity: optimistic, pessimistic, and most likely
-
you have to find the Critical Path. The Critical Path is the longest path of scheduled activities that must be met in order to execute a project. It is important to know because any problems on the critical path can prevent a project from moving forward and be delayed. Therefore only critical activities can contribute to the project variance.