Answer:
Total cost= $58,150
Explanation:
Giving the following information:
Molding Finishing Total
Estimated total machine-hours (MHs) 5,000
Estimated total fixed manufacturing overhead cost $17,400
Estimated total variable manufacturing overhead= (3*3,250 + 6*1,750)= $20,250
<u>First, we need to calculate the predetermined overhead rate:</u>
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (17,400 + 20,250) / 5,000
Predetermined manufacturing overhead rate= $7.53 per machine hour
<u>Now, we can calculate the total cost:</u>
<u />
Total cost= 10,100 + 10,400 + (7.53*5,000)
Total cost= $58,150