Answer:
The difference in the direct materials cost per equivalent unit between the two months is $0.70.
Explanation:
First calculate the direct cost per equivalent unit in September
Direct cost per equivalent unit = Total Cost / Total Equivalent units
= $12,000 / 7,500
= $1.60
<u>Difference between the two months.</u>
September = $1.60
Less August = ($0.90)
Difference = $0.70
Answer:
The actual price = $1.08
Explanation:
The standard material price can be worked out as follows:
<em>Step 1: Work out the standard price of material using the material usage variance</em>
Standard price = Material usage variance/(standard quantity of material - actual quantity)
Standard quantity of material = standard qty per unit × actual production
= 4 × 17,000 =68,000
Standard price = 2,800/(68,000-64,000)= $0.7
<em>Step 2 : Work out the Actual material price using the material price variance</em>
Material price variance = (Standard price - Actual price )× Actual quantity of material
6,400 = (y - 0.7) × 17,000
6400 = 17,000y - 11,900
17,000 y = 6,400 + 11,900
y = 18,300/17,000= 1.08
The actual price = $1.08
The correct answer is A; Change in project scope.
Further Explanation:
The project has now changed drastically from Beta tapes to VHS. With this happening, all of the work they had did on the Beta tapes is now null. The company will now have to change the scope of their work to working with VHS tapes.
A few of the things that will have to be done to change the scope of project are;
- quality can be changed or modified
- new costs
- new tasks
- new deadlines
- more money needed to invest
- functions
Learn more about project scopes at brainly.com/question/13234457
#LearnwithBrainly