Answer: See explanation
Explanation:
a. The actual direct labor rate per hour will be:
= Standard direct labor rate per hour - favorable labor rate variance
= $11 - $0.40
= $10.60
Then, the actual direct labor hours worked during July will be calculated as:
= (5910 × $11) - $350 / $10.6
= ($65010 - $350) / $10.6
= $64660 / $10.6
= 6100
b. The direct labor rate variance will be:
= (Actual rate per hour - standard rate per hour) × Actual labor hours
= (10.60 - 11.00) × 6100
= 2440F
Direct labor efficiency variance will be:
= (6900 - 5910) × $11
= 2090U
The direct labor rate variance that was favorable shows that the manager paid a lower rate to its staffs while the direct labor efficiency variance that was unfavorable implies that the manager used less efficient workers. This indicates that a trade-off took place.
= (6900
Answer:hgjugvycuuhubhbhhb
Explanation:gvrdedbuhgfryyikjngvfvtfvrt
Do not do
text, drink, speed
do
watch road, hands on wheel, be safe
Answer:
d. A temporary endeavor undertaken
Explanation:
- A project is a continuous business and a society that is treated a project and any interesting carrying out individually or collaboration and possible moving the research. The design that is carefully planned to get to a particle aim and maybe termed and constitutes to the tms and to accomplish a particular tasks under the time constraints.
Answer:
a-1. NPV for the project is $8,381,576.17
a-2. A. Yes. Accept the Project.
b. 40.84 % and 40.84 %
Explanation:
The Net Present Value can be determined using a Financial Calculator as follows :
-38,600,000 CFj
62,600,000 CFj
- 11,600,000 CFj
11 % I/YR
Shift NPV $8,381,576.17
A Company should accept projects that have a positive Net Present Value.Therefore, Accept this project.
Calculation of the Internal Rate of Return using a Financial Calculator :
-38,600,000 CFj
62,600,000 CFj
- 11,600,000 CFj
Shift IRR 40.84 %