Using multiple cost drivers on a flexible budget report will generally make the budget accurate and effective.
<h3>What is flexible budget performance report?</h3>
A flexible budget performance report serves as one that make comparison between actual revenues and costs for a period.
There are some method used in estimating this report, but multiple cost drivers is an effective method to get an accurate report.
Learn more about flexible budget performance report at:
brainly.com/question/27201970
Answer:
Y= 6000 + 0.75X
Explanation:
High and low cost technique
Using the a high and low technique, total cost can be analysed and separated into fixed and variable portion. This analysis helps in the forecast of cost and therefore important for the preparation of budget.
<em>Variable cost of maintenance</em>
= (Cost at high activity - Cost at low activity)/ (high activity - low activity)
VC per act. = ( $15000 - $12000)/(12,000-8000)
= $0.75 per activity
<em>Fixed cost of maintenance</em>
= Total cost at high activity - (VC per act × high activity)
= $15,000 - ( $0.75 × 12,000)
= $6,000
The cost formula will be:
Y= 6000 + 0.75X
Where Y = maintenance cost, X= level of activity
Answer:
Explanation:
Topic chosen is - HR manager, this position interest me because it would help to improve my managerial skills, it will as well help me to know other people and how to handle and understand them.
For this position, i went online for 15 min. collected information on job site like linkedin , monster, indeed, glassdoor etc. to gather as much information as possible.
From Linkedin i get to know the avg salary of HR manager is about $100,600 per annum.
From Indeed i was able get recent information of a job position vacancy for HR evecutive position in Tech company.
I wsa able to gather that HR manager position is for experienced person at least 3 years of experience and required many skills like planning, analytical, communication, technical skills. etc.
Within 15 mins of my research i had clear mind about my interest in HR and i gather information as where to start my my career
Answer:
$214,500
Explanation:
For the computation of the amount of contribution margin first we need to follow some steps which are shown below:
No of units sold = Total sales ÷ selling price per unit
= $374,400 ÷ $24
= $156,00
Variable cost = No of units sold × Variable cost per unit
Variable cost = $15,600 × $13
=$202,800
Contribution margin = Sales - Variable cost
= $374,400 - $202,800
= $171,600
CM ratio = Contribution margin ÷ Sales
= $171,600 ÷ $374,400
= 0.46
Contribution margin = CM ratio × Sales Contribution margin
= 0.46 × (1.25 × $374,400)
= $214,500
Answer:
By using the percentage-of-completion method the $64 million revenue should Parmac recognize in 2018
Explanation:
Percentage-of-completion method : Under this method,
First we have to calculate the percentage which is based on current period cost to total period cost.
After that, multiply the percentage with the revenue so that we get to know how much revenue is being recognized during an particular year.
In mathematically,
Estimated Cost percentage = current period cost ÷ total period cost
= $48 million ÷ $120 million
= 40%
Now,
Revenue recognized = Estimated cost percentage × Revenue
= 40% × $160 million
= $64 million
Hence, by using the percentage-of-completion method the $64 million revenue should Parmac recognize in 2018