Thank you for posting your question here at brainly. I hope the answer will help you. Feel free to ask more questions.
i think the answer is B which is <span>Timber land was harvested, robbing Native Americans of a valuable resource</span>
An employement contract if Edna is unable to complete the procedure, another surgeon with the minimum degree of expertise required for the procedure must take over the contract.
This example’s procedure is risky and connected to a risky surgery that would be best handled by Edna. Since the contract was based on Edna’s experience, it cannot be transferred to someone with the lower level of expertise required for this activity.In this case, Edna, a renowned brain surgeon in the United States, signs a contract to operate delicately on Ben’s brain. Edna, who has a lot going on, wants to give Charles, a less experienced surgeon who would be doing his first procedure of this kind, this contract because she is so busy.Because the contract between Ben and Edna involves personal talent, Ben can object to and stop this assignment (brain surgery).Evidently, Edna’s position as the top brain surgeon in the USA can be attributed to her competence and professionalism. With this knowledge at his disposal, Ben decided to enter into a contract with Edna, a skilled brain surgeon.
To know more about Edna visit:
brainly.com/question/14264438
#SPJ4
Answer:
c.Rents occur at the beginning of each period of an annuity due.
Explanation:
First, know the difference between Ordinary annuity and Annuity due.
In Ordinary annuity, recurring payments occur at the end of the payment period; for example at the end of every month, end of ever year , end of every quarter etc.
On the other hand, in the case of Annuity due, the recurring payments occur at the beginning of the period like at the beginning of the month, beginning of the year;Jan 1st, or beginning of every quarter
In the case of rent, tenants pay rent at the beginning of each month making this type of payment an Annuity Due.
Based on the activity times, and the order of activities, the critical path is B ⇒ E ⇒ G ⇒ H.
The slack for Activity A is 8 weeks and the slack for Activity D is 8 weeks as well.
<h3>What is the critical path?</h3>
First find all the possible paths:
- A ⇒ D ⇒ F ⇒ H - 21 weeks
- B ⇒ D ⇒ F ⇒ H: 18 weeks
- B ⇒ E ⇒ G ⇒ H: 29 weeks
- C ⇒ G ⇒ H: 26 weeks
- C ⇒ F ⇒ H: 20 weeks
The critical path takes the longest time so will be B ⇒ E ⇒ G ⇒ H: 29 weeks.
<h3>What is the slack for Activity A?</h3>
This can be found as:
= Latest finish for A - Earliest finish for A
Looking at the network, the earliest finish for A is 5 and the latest finish is 13.
Slack is:
= 13 - 5
= 8 weeks.
<h3>What is the slack for activity D?</h3>
Earliest finish for D is 7 and lastest finish is 15.
Slack is:
= 15 - 7
= 8 weeks.
Find out more on the critical path at brainly.com/question/8147877.
Answer:
a. 30 million
b. 60%
c. 33.33%
Explanation:
The computation is shown below:
a) Labor force = employed + unemployed
= 20 million + 10 million
= 30 million
b) Labor-force participation rate = Labor force ÷ Working age population
= 30 million ÷ 50 million
= 60%
c) Official unemployment rate = unemployed ÷ labor force
= 10 million ÷ 30 million
= 33.33%