5

Cordner Corporation has two production Departments: P1 and P2 and two service departments: S1 and S2. Direct costs for each depa

rtment and the proportion of service costs used by the various departments for the month of July are as follows: Proportion of Services Used S1 Department S1 S2 P1 P2 Direct costs $180,000 $162.000 $ 197000 $140000 S2 0.70 P1 0.10 0.300.50 P2 0.20 0.20 Under the step-method of cost allocation, the amount of costs allocated from $2 to P2 would be_________________.a. $81000b. $84 250c. $180,000d. $93.500
Business
1 answer:
Goryan [66]3 years ago
5 0

Solution:

S1  $180,000 is allocated 70% to S2 or $126,000 ( 0.7 * 180,000 )

S2  total is $162,000 + $126,000 = $288,000

S2  $126,000 is allocated 19.7% to P2 or $81000

Under the step-method of cost allocation,

the amount of costs allocated from $2 to P2 would be $81000

You might be interested in
Hoi Chong Transport, Ltd., operates a fleet of delivery trucks in Singapore. The company has determined that if a truck is drive
Anvisha [2.4K]

Explanation:

The computation of the fixed cost and the variable cost per hour by using high low method is shown below:

Variable cost per hour = (High Operating cost - low operating cost) ÷ (High driven in kilometers - Low driven in kilometers)

where,

High operating cost = 114,000 km × 12.7%

= $14,478

Low operating cost = 76,000 km  × 14.8%

= $11,248

So,

= ($14,478 - $11,248) ÷ (114,000 km - 76,000 km)

= $3,230 ÷ 38,000 km

= $0.085 per km

Now the fixed cost equal to

= High operating cost - (High driven in kilometers × Variable cost per km)

= $14,478 - (114,000 km × $0.085)

= $14,478 - $9,690

= $4,7882

2. The equation is as follows

Y = a + bx

So,

Total cost = $4,788 + 0.085X

3.

Y = a + bx

   = $4,788 + 0.085 × 95,000

   = $4,788 + $8,075

   = $12,863

5 0
3 years ago
If interest rate on 1-year unsecured loan is 4.5%p.a. The inflation rate is 3.2% this year. What is the real interest rate?
Alexeev081 [22]

Explanation:

Jehsjj&( djshd kdkduryyhrhe tjrhrhrh

8 0
3 years ago
A current warehouse system has five warehouses with 4,000 units at each warehouse. The company desires to change to three wareho
miskamm [114]

Answer:

Correct option is C.

15492 is the average ware-house inventory level.

Explanation:

A current warehouse system has five warehouses with 4,000 units at each warehouse. The company desires to change to three warehouses to become more centralized and keep the same customer service levels.

Average warehouse inventory levels =4000*5*(3/5)0.5 =15492

3 0
3 years ago
Which estimating technique uses a statistical relationship to calculate cost or duration based on historical data and other proj
Yuliya22 [10]

Answer:

parametric estimating

Explanation:

parametric estimating - it is referred to as a technique that is induced to calculate the exact cost and duration for any project. It defined the relationship between the variables (published data) needed to estimate the cost and duration. it determined the total number of units that need to be required and unit cost for a particular project. The main application of this technique is seen in filed like engineering, life science, etc.

3 0
3 years ago
Planned sales for June this year are $120,000. Last year, the actual sales for June were $110,000. Determine the planned percent
Leni [432]

Given that the planned sales for June this year are $120,000 and that last year's actual sales for the month of June were $110,000, there is a 9.09% increase in sales for the month.

The actual increase in sales is $10,000 ($120,000 - $110,000) or ($110,000 x 1.0909 - $110,000)

Data and Calculations:

Planned sales for June, this year = $120,000

Actual sales for June,last year = $110,000

Planned percent increase in sales for June = 9.09% ($10,000/$110,000 x 100)

Thus, the planned percentage increase in sales for the month is 9.09%.

Learn more: brainly.com/question/17194869

6 0
3 years ago
Other questions:
  • Metaline Corp. uses the weighted average method for inventory costs and had the following information available for the year. Eq
    6·1 answer
  • While an attribute is an inherent quality or characteristic of a product or service, a(n) _____________ is a result or outcome a
    6·1 answer
  • The three-legged Ork, a space creature from the universe Warhammer, wears 1 right shoe and 2 left shoes. Which set of market bun
    12·1 answer
  • Need answers fast comment and ill answer as fast as I can starting with who asked first
    10·2 answers
  • Clem Corporation issues 1,000 shares of common stock for $25,000. Clem purchased equipment for $10,000 by borrowing from the ban
    6·1 answer
  • Job applicants generally face two kinds of interviews: screening interviews and hiring interviews. You will be better prepared i
    13·1 answer
  • During a natural disaster, such as a hurricane, the demand for hotel/motel rooms in an area can suddenly surge, driving up the p
    10·2 answers
  • When coffee Is traded between countries it is called a________.
    12·1 answer
  • Uma has been given the task of arranging for five-day conference
    12·1 answer
  • Factors of production examples ​
    9·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!