Answer:
B. increases; increases
Explanation:
<em>As the interest rate increases, the money invested today will bring higher interest in the future. </em>
For example if you lend $1,000 and the interest rate is 4% you will receive $1,040 after one year, if the interest rate is 6% your money will become $1,060
<em>Future value should be higher the longer money is invested because the borrower should be able to do more activities that bring profit. </em>
For example if you lend $1,000 and the interest rate is 4% you will receive 1,000x(1+0.04) = $1,040 dollars after one year and 1,000x = $1081 after 2 year
Waterways (ships and such), roads (trucks, bikes and such) and air (planes, helicopters, drones). hope this helps a little
Eather decide to buy the movie cuz she has the money or decide aginst it becuase she doesnt have the money
Answer:
The correct answer is b. after taxes minus preferred dividends.
Explanation:
Net profit: Add all the revenues of the firm and deduct all the expenses of the firm. If the amount come in positive, the firm earns profit else suffered loss.
In mathematically,
Net profit = Sales revenue - all expenses
The earning which is available to shareholders is net profit after paying preference dividend to preference shareholders.
As first we have to pay the dividend to preference shareholders then we distribute the income to equity shareholders.
In mathematically,
EBIT - taxes - Preferred dividend
Hence, the correct option is b. After taxes minus preferred dividends.
Answer:
See below
Explanation:
1. Total materials variance
= (Actual quantity - Actual price) - (Standard quantity × Standard price)
= $4,410 - [(160 × 9) × $1.9]
= $4,140 - $2,736
= $1,404 unfavorable
2. Materials price variance
= (Actual quantity × Actual price) - (Actual quantity × Standard price)
= $4,140 - (2,100 × $1.9)
= $4,140 - $3,990
= $150 unfavorable
3. Materials quantity variance
= (Actual quantity × Standard price) - (Standard quantity × Standard price)
= (2,100 × $1.9) - [(160 × 9) × $1.9]
= $3,990 - $2,736
= $1,254 unfavorable
4. Total labor variance
= (Actual hours × Actual rate) - (Standard hours - Standard rate)
= $6,664 - (160 × 4) × $10
= $6,664 - $6,400
= $264 unfavorable