Barry Gross is an organizer and leader of BillCutter.com that was built up in 2009 with the primary reason for giving administrations to the clients who needs to spare cash on service bills. He had an exceptional vision prompting a foundation of novel administrations with no immediate rivalry in the business. Barry's past experience incorporates quite a while of phone deals which helped him with transaction aptitudes which he utilized towards utility suppliers in the interest of his clients.
Answer:
С. $1,350.00 Favorable
Explanation:
The computation of the material price variance is shown below:
= Actual Quantity × (Standard Price - Actual Price)
= 9,000 × ($19.15 - $171,000 ÷ 9,000)
= 9,000 × ($19.15 - $19)
= 9,000 × $0.15
= $1,350 favorable
The actual price is computed below:
= Actual cost of materials purchased ÷ Actual materials purchased
= $171,000 ÷ 9,000
= $19
Answer:
The cost of the depreciation of plant's machinery is considered a variable cost because machinery uses an accelerated depreciation method for book and income tax purposes
Explanation:
A variable cost is an expense that is proportional to the production output. That is variable costs increase or decrease with respect to a company's production. This cost rise as production rises and falls as production falls. Costs of raw materials and packaging are examples of variable costs.
Here,
Corporation, a manufacturing company, is analyzing its cost structure in a project to achieve some cost savings.
The cost of the depreciation of plant's machinery is considered a variable cost because machinery uses an accelerated depreciation method for book and income tax purposes
Answer:
Complexity
Explanation:
As an innovation reduces the difficult of a certain activity or process it will have a better reception and therefore, a higher rate of diffusion.
The Toaster-matic 2000 has a knowledge barrier thus, while there is relative advantage(better benefit than any competition) in his use the diffusion is diminish <u>by his complexity. </u>
<u />
Answer:
Direct material quantity variance= $850 unfavorable
Explanation:
Giving the following information:
Standard tons of direct material (steel) per car 4
Standard cost per ton of steel $ 17.00
During March, the company produced 1,650 cars.
Actual materials purchased and used (tons) 6,650
<u>To calculate the direct material quantity variance, we need to use the following formula:</u>
<u></u>
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (4*1,650 - 6,650)*17
Direct material quantity variance= $850 unfavorable