Relationship of the firm to other economic agents.
Explanation:
Economics is a branch of social science where it shows the relation between the firm as well as other economic agents. The economic agents can interact individually as well as in an aggregate way. An economic agent is referred to as decision maker that can effect the economy at the time of selling, producing, buying. The various examples of economic agents are firm, households, individuals as well as business.
In this context NYC is a firm and the rent guideline boards as well as the landlords are various economic agents. In this context a relationship is shown between the firm and the economic agents.
Answer:
option (C) 32,750 hours
Explanation:
Data provided in the question:
Actual manufacturing overhead cost = $250,000
Overapplied overhead = $12,000
Predetermined overhead rate = $8.00 per direct labor-hour
Now,
The total Manufacturing Overhead applied last year
= Actual manufacturing overhead cost + Overapplied overhead
= $250,000 + $12,000
= $262,000
Therefore,
Direct Labor Hours worked last year =
or
=
= 32,750 hours
Hence,
The correct answer is option (C) 32,750 hours
If an electrical disturbances are recorded over an extended period and the monitoring equipment indicates they are on the utility side of the PCC, in order to remedy the disturbances, the utility should be informed of the monitored events.
<h3>What is an electrical disturbance?</h3>
This refers to an electrical or magnetic damage, disturbance of electronic recordings or erasure of electronic recordings. This disturbance encompasses 3 broad categories which includes an electrical or magnetic damage, electronic recording disturbances, and erasure of electronic recordings.
An Electrical Design Power hardware and software is very susceptible to these electrical disturbances. The most common electrical disturbance losses are damaged circuitry, erroneous results, loss of data, system failure, and system shutdown. As well, these electrical disturbance is normally excluded from property coverage forms which is one of the main reasons to buy specialized EDP coverage
Read more about electrical disturbance
brainly.com/question/9278918
#SPJ1
Answer:
Cycle Time = 10.19482 minute
Explanation:
From the question :
The Model E can be illustrated perfectly as shown below:
Process Time Required Predecessor Task Learning Rate
per Unit
A 9 82
B 12 A 86
C 18 B 81
D 9 C 90
E 12 D 80
F 17 E 88
G 14 F 83
H 12 G 85
I 8 H 82
Now For the minutes per week for each Process; we have :
Process Time Required Predecessor Learning Minutes
per Unit Task Rate (Week 16)
A 9 82 4.069096
B 12 A 86
6.564098
C 18 B 81 7.74841
D 9 C 90 5.9049
E 12 D 80 4.9152
F 17 E 88 10.19482
G 14 F 83 6.644165
H 12 G 85 6.264075
I 8 H 82 3.616974
The objective here is to determine the expected Cycle Time for Model E in Week 16
So, we can equally regard the Cycle Time = Bottleneck of Activity for Week 16.
Cycle Time = 10.19482 minute in as much as it is the the largest activity time for the week 16
Given that the demand per week is : = 247
The available time per week = 40 hours = 40 × 60 hours = 2400 minutes
Talk Time = Available Time Per Week/Demand Per Week
Talk Time = 2400/247
Talk Time = 9.716599
Thus; here the cycle time is greater than the talk time.