Answer:
Option (a) is correct.
Explanation:
Given that,
Completed units during June = 65,000 units
Ending inventory units = 7,000 units
Beginning inventory units = 4,000 units
Number of material equivalent units of production in the June 30:
= Completed units during June + Ending inventory units - Beginning inventory units
= 65,000 units + 7,000 units - 4,000 units
= 68,000 units
Therefore, the number of material equivalent units of production is 68,000 units.
Answer:
$259.34
Explanation:
the value of the stock can be determined using the two stage dividend discount model.
In the first stage, the present value would be determined using a discount rate of 18%.
In the second stage, the present value would be determined using a discount rate of 6%.
Values from the first and second stage would be added together to determine the value of the stock
First stage
Present value in year 1 = ($3.2 x 1.18) / 1.087 = $3.47
Present value in year 2 = ($3.2 x 1.18²) / 1.087² = $3.77
Present value in year 3 = ($3.2 x 1.18³) / 1.087³ = $4.09
Present value in year 4 = ($3.2 x 1.18^4) / 1.087^4 = $4.44
Second stage
($3.2 x 1.18^4 x 1.06) / (0.087 - 0.06) = 243.57
Value of the stock = $3.47 + $3.77 + $4.09 + $4.44 + 243.57 = $259.34
Answer:
The fixed costs are too high. The marginal cost generally represents variable costs and they might be very low, but if the fixed costs are simply too high, they will need to increase the price of the plane tickets in order to break even. The break even formula is calculated by dividing total fixed costs by marginal revenue (selling price - variable costs).
Answer:
If an activity has a slack value greater than zero, it needs to be a critical activity
Explanation:
The false statement in the group of answer choices is If an activity has a slack value greater than zero, it needs to be a critical activity this is because for an activity to be considered a critical activity its slack value has to be equal to zero and not greater than zero,
activities with critical value greater than zero are considered just activities and not critical activities because there is time range given to the activity