Answer: Project X
Explanation:
The Payback period is the amount of time it would take for the cash inflows accruing from an investment to payoff the cost of the investment.
Project X has a constant cashflow of $24,000 for 3 years and a cost of $68,000 for the Payback period is;
= 68,000/24,000
= 2.83 years
Project Y has an uneven cash flow with a cost of $60,000. Payback is calculated as;
= Year before payback + Amount left to be paid/cashflow in year of payback
Year before payback = 4,000 + 26,000 + 26,000
= $56,000
This means that the third year is the year before payback.
60,000 - 56,000 = $4,000
Payback period = 3 + 4,000/20,000
= 3.2 years
Based on a Payback period of 3 years, only Project X should be chosen as it pays back in less than 3 years.
Answer:
14,275= actual hours
Explanation:
Giving the following information:
The standard for a particular crane calls for 14 direct labor-hours at $16 per direct labor-hour.
During a recent period, 1,000 cranes were made.
The labor efficiency variance was $4,400 Unfavorable.
To determine the actual hours worked, we need to use the direct labor efficiency variance formula:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
-4,400= (14*1,000 - actual hours)*16
-4,400= 224,000 - 16actual hours
228,400/16= actual hours
14,275= actual hours
Answer:
a) safety stock = z-score x √lead time x standard deviation of demand
z-score for 99.9% = 3.29053
√lead time = √7 = 2.6458
standard deviation of demand = 3
safety stock = 3.29053 x 2.6458 x 3 = 26.12 ≈ 26 soaps
reorder point = lead time demand + safety stock = (7 x 16) + 26 = 138 soaps
EOQ = √[(2 x S x D) / H]
S = order cost = $10
D = annual demand = 16 x 365 = 5,840
H = $0.05
EOQ = √[(2 x $10 x 5,840) / $0.05] = 1,528.40 ≈ 1,528 soaps
b) total order costs per year = (5,840 / 1,528) x $10 = $38.22
total holding costs = (1,528 / 2) x $0.05 = $38.20
total annual ordering and holding costs = $76.42
Answer:
$795.5
Explanation:
To calculate how much 0.9% income they have to pay, the law says anybody that earns above 250000 as married couple is entitled to pay above 0.9%, so for them we will subtract the 250000 from it and also Ruth loss of 13,500
So we have;
(3520000-13500-250000)*0.9%=
$796.5
A. Bid/no bid decision
A "bid" is what contractors call their proposals, and in some cases it will not be worth it to even submit a proposal on a job. The stage where contractors decide if it is worth it is called bid/no-bid.