Answer:
The correct answer is the option B: Activity B.
Explanation:
First of all, the term <em>''bottleneck''</em> in the management area refers to the activity or process in a chain of processes that its limited capacity reduces the capacity of the chain in its whole.
Once said that, in the case presented, where there are four workers and two of them have to do two differents tasks then the activity consider the bottleneck of the process will be the one in where one person does an activity after another and that reason makes that person delates more in working. That is the case of the activity B, where Aaron has to work again after the first activity and that takes him and Betty five minutes full, while in the other case where Betty works with David they only take four minutes, so therefore that the activity B is the bottleneck of the process.
Answer:
The answer is A.
Explanation:
Other things remaining equal, the law of demand says that the higher the price, the lower the quantity demanded and the lower the price the higher the quantity demanded.
Suppose a good is being sold at $5 and 20 quantities are being demanded, if the price increases to $6, lesser of that goods should be demanded
An example of a natural monopoly industry operating in South Africa include "Eskom".
<h3>
What is natural monopoly?</h3>
A natural monopoly occurs when there is an instance in which it is economically viable and better for a single entity to be in full and sole control of the production of a product or service.
Moreover, a natural monopoly is the fact that natural monopolies have extreme economies of scale. It can only start to become profitable when one single firm is able to service the majority of the market.
Learn more about natural monopoly, refer to the link:
brainly.com/question/4417882
#SPJ1
The short-run average total cost of Ike's Bikes of producing 100 bikes is $360.
<h3>
What is the short-run average total cost ?</h3>
The short-run is a production period where some of the factors used in the production process are fixed and others are variable. The short-run average total cost is the total cost divided by total output. Total cost is the sum of fixed cost and variable cost.
Please find attached the complete question. To learn more about average cost, please check: brainly.com/question/26959638
Answer:
3
Explanation:
We are asked to use the midpoint formula.
Here, instead of dividing the change in values by the old value as in the normal elasticity calculation, we use the average of the two.
Mathematically:
Price elasticity of demand according to midpoint formula is :
{Q2 - Q1 / (Q2 + Q1) ÷ 2] × 100%} ÷ {[P2 - P1/ (P2 + P1) ÷ 2] × 100}
Price changed from 5 to 7. The midpoint of 5 and 7 is the average = (5+7)/2 = 6
% change in price in this case is (7-5)/6 * 100 = 100/3 = 33.33%
% change in quantity:
We first find the average = (12+4)/2 = 16/2 = 8
% change = (4-12)/8 * 100 = -100%
The elasticity of demand is thus -100/33.33 = 3