CodeHead Software Inc. does software development. One important activity in software development is writing software code. The m

anager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer's hourly rate to increase to $40.00 per hour during the first week in May. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If an amount is zero, enter "0" and choose "Not applicable" from the dropdown.
If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance?
Business
1 answer:
Irina18 [472]3 years ago
4 0

Answer:

Explanation:

Standard hours per week = 40 hours

Standard rate per hour = $32

Actual rate per hour = $40

Labour rate variance = 40 - 32 = $8 (unfavourable)

Actual cost per week = 40 × 40 = $1600

Standard cost per week = 40 × 32 = $1280

Labour cost variance = actual cost per week - standard cost per week

= 1600 - 1280

= $320 (unfavourable)

Actual codes written in first week = 5650

Standard codes per week = 5 × 25 × 40 = 5000

Actual cost per code = 1600/5660 = $0.2832

Standard cost per code = 1280/5000 = 0.256

Labour efficiency variance = 0.2832 - 0.256 = $0.0272 (unfavourable)

If the team generated 4,650 lines of code according to the original plan:

Code generated = 4650

Number of programmers = 5

Average codes per hour per programmer = 25

Total codes per hour = 25 × 5 = 125

Standard codes per week = 40 × 125 = 5000

Actual time to write 4650 codes = 4650/125 = 37.2 hours

Standard time = 40 hours

Idle time = 40 - 37.2 = 2.8 hours

Labour time variance = 2.8 hours

Cost of idle time = 2.8 × 32 = $89.6 (unfavourable)

You might be interested in
Contribution margin is always the same as gross profit margin. is calculated by subtracting total manufacturing costs per unit f
goldfiish [28.3K]

Answer: equals sales revenue minus variable costs

           

Explanation: In simple words, contribution margin refers to the amount of revenue that an organisation is left with after paying for the variable expenses that are incurred for the generation of such revenue.  

It is an important aspect of an organisation as it somehow depicts the ability of it to pay its fixed expenses like interests etc.

7 0
3 years ago
Dakota Products uses a job-costing system with two direct-cost categories (direct materials and direct manufacturing labor) and
IRISSAK [1]

Answer:

1.Overhead Rate = Overhead Costs/ Direct Labor Costs

Budget Overhead Rate = 3060,000/ 1700,000= 1.8

Actual Overhead Rate = 3217,500/ 1650,000= 1.895

Dakota Products

                                Budget for 2017                  Actual Results for 2017

Direct material costs $2,250,000                          $2,150,000

Direct manufacturing labor costs 1,700,000          1,650,000

Manufacturing overhead costs 3,060,000            3,217,500

2.During March, the job-cost record for Job 626

Direct materials used $55,000

Direct manufacturing labor costs $45,000

Actual Overhead  = 1.895 * $45,000= $ 85295.45

Normal Overhead = 1.8 * 45,000= $ 81,000

2.The  actual cost of Job 626 =$ 55,000+ $ 45,000+ $ 85295.45= $ 185,295.45

2.The  normal cost of Job 626 =$ 55,000+ $ 45,000+ $ 81,000= $181,000

3. Under- or Overallocated Overhead under normal costing=

     Budgeted Overhead - Actual Overhead= 3,060,000 -  3,217,500=

157,500 underapplied

There is no under- or overallocated overhead under actual costing because  overhead costs actually are at their actual costs. There is no difference between calculated and actual.

4. Normal Costing would give an idea before 2017 and it is easier to make decision prior to changes. Actual results can only be obtained after the process. Managers find it easier to pre plan . So normal costing is adoptable.

4 0
3 years ago
When the economy is on the short-run aggregate supply curve and to the left of the long-run aggregate supply curve, actual aggre
Colt1911 [192]

Answer:

Nominal salaries decrease and the short term aggregate goes up to the right.

Explanation:

Companies normally make decisions about the amount of supplies in which they invest according to the profits that they expect to obtain in the future according to the variables of their economic activity. The profits for the company will be also determined by the price of the products or services the company trades and the price of the supplies necessary for such activities.

6 0
4 years ago
How could government – sponsored grants for the private development of new technologies result in a lower national debt?
Svet_ta [14]

Answer: Making initial development private saves the government from funding all of the research.

Explanation:

A grant refers to an amount of money that is financial assistance thats given by the government or an organization to an individual or firm for a specific purpose. A grant is different from a loan as it isn't meant to be paid back.

Government award grants for the development of technologies, community projects, home insulation etc.

With regards to the question, a government – sponsored grants for the private development of new technologies may result in a lower national debt when the government makes the initial development private thereby saving the government from funding all of the research.

6 0
3 years ago
A sporting goods manufacturer budgets production of 48,000 pairs of ski boots in the first quarter and 39,000 pairs in the secon
professor190 [17]

Answer:

$831,600

Explanation:

The budget must account for all of the production of the first quarter and 20% of the production of the second quarter, the number of boots considered in the budget is:

b= 48,000 +0.20*39,000\\b=55,800\ boots

Assuming that each boot uses exactly 2kg of raw material and that the company has 19,200 kg on hand, the amount of raw material still required is:

m = 2*55,800-19,200\\m=92,400\ kg

If the cost per kg is $9, then the budgeted materials purchases cost for the first quarter is:

C=92,400*\$9\\C=\$831,600

The budgeted materials purchases cost is $831,600.

5 0
3 years ago
Other questions:
  • A marketing manager had a goal to improve market share for his paper plates by 2 percent in the coming year, and he felt he’d ne
    15·1 answer
  • Research has shown that the association between job satisfaction and job performance is ________.
    8·1 answer
  • ou open a business selling art supplies and lessons. In your first month, you had the following total sales: $4,000 in paint, $2
    15·2 answers
  • If a firm invests in continuous innovation and willingly cannibalizes its existing products with more advanced products, the fir
    9·1 answer
  • Which item(s) are tax deductible for consumers who are buying or renting a home?
    9·2 answers
  • Which one of the following descriptions best describes horizontal integration? 1) the economic development of the American West
    12·1 answer
  • A small business owner has decided to form a ______________ after deciding that she wants to maximize revenue, minimize taxes, g
    11·1 answer
  • According to the principle of __________, the more recent the data, the more valuable they are.
    15·1 answer
  • Economists define potential income as the level of income that: Group of answer choices an economy is capable of producing witho
    7·1 answer
  • Both IFRS and U.S. GAAP allow deferred taxes to be: presented as noncurrent on the balance sheet. measured using a substantially
    11·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!