Answer:
Materials cost per unit is $13.40
Explanation:
Equivalent Unit of Material = (3,200-1,700)*100% + 1,700*100%
Equivalent Unit of Material = 3,200
Materials cost per unit = total materials costs/Equivalent Unit of Material
Materials cost per unit = 42,880/3,200
Materials cost per unit = $ 13.40
Answer:
Option "b"$55000 is correct.
Explanation:
Below is the given values:
Starting raw material = $30000
Pruchased material = $65000
Raw material at the end = 40000
Now calculate the raw material used:
Raw material used = Starting raw material + purchases - ending raw material
Raw material used = 30000 + 65000 - 40000
Raw material used = 95000 - 4000
Raw material used = $55000
Thus option "b"$55000 is correct.
Answer: The correct answer is option (A)
Explanation: Activity rates is calculated by dividing the budgeted activity cost by the total activity-base usage.
Activity Rate = (Budgeted Activity cost) ÷ ( total activity base usage)
Perfections
This was tricky ! Was there no options?