I think the answer would be "superscript"
Answer:
Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration
Answer: Progress report presentation
Explanation: Progress report presentation is the presentation that consist the progress report of an individual's work .It describes about the project/work that a person has started to complete the project. These reports are made for the clients, students, colleagues etc.
Progress report in this case is made for the client to make them understand about the Jeff's work , his contribution, changes he invoked in it, achievements ,completion of the project, benefits of it etc. This presentation will encourage the client to buy the software made by Jeff.
I believe it is a white curb!
Answer:
myInt=40
myFloat=4.8
Explanation:
First look at the function definition .It has two arguments intVal is passed by reference while floatVal is passed by value.So the changes done on the myInt variable will be reflected on the original argument because when a variable is passed by reference the the changes are reflected on the original argument but when a variable is passed by value the function created a duplicate copy of it and work on them so changes are not reflected on the original argument.So myInt will get doubled while myFloat will remain the same.