Answer:
The answer is: B) The reduction in economic surplus resulting from a market not being in competitive equilibrium.
Explanation:
Deadweight loss is an economic cost to society as a whole when market inefficiencies occur preventing it from reaching its equilibrium point. Market inefficiencies are caused by incorrect allocation of resources.
For example if a price ceiling is established, suppliers will tend to lower the quantity supplied while the quantity demanded either increases or stays the same. That economic deficiency resulting from an unsatisfied demand is what we call deadweight loss.
Other causes for deadweight loss are price floors (reduction of the quantity demanded) and taxation (shifts on the demand or supply curves).
Answer:
15 and I lost it but not by choice
Accomplishment is the correct answer
Answer:
Net loss $100,000
Explanation:
<em>The relevant cost for decision to accept the special order are
</em>
<em>I Incremental Revenue from the special order
</em>
<em>2. incremental variable cost</em>
<em>Note that whether or not the special order is accepted the fixed manufacturing and fixed operating expenses of would be incurred either way. Therefore , they are not relevant for the decision</em>
<em />
Variable cost cost= 40 +10= 50
Sales revenue from the special order $
(45 × 20,000) 900000
Variable cost of the special order (50× 20,000) <u>(1,000,000 ) </u>
Net loss <u>100,000</u>
Complete Question:
<em>What term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities?</em>
Answer:
Free slack.
Explanation:
Free slack is a term is used for the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
Generally, in the execution of a project, when a task is delayed it normally affects the start or finishing time of the other tasks (successors) in a project. The amount of time that is permitted for an activity to be delayed without delaying the early start date of any immediately following (succeeding) activities refers to the free slack or having an adverse effect on entire project.