15 electricians worked for 24 days to the whole job, now, there are 15 of them, so on any given day, each electrician worked one whole day, in 24 days, that one electrician worked 24 days total.
now, there were 15 electricians on any given day though, since each one of them worked the whole day that one day, so the "days work worth" on a day is 15, so the house gets 15days worth of work because of that.
so how many "days worth" did all 15 do on the 24 days, well, 15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15+15, namely 15 * 24, or 360 days worth of work.
since it takes 360 days worth of work to do the whole wiring, in how many days would 18 electricians do it? 360/18.
9514 1404 393
Answer:
$170
Step-by-step explanation:
If the price of a pair of Jordans is the same as the price of two shirts, the total purchase has a value equivalent to that of 3 Jordans.
pair of Jordans = $510/3 = $170
That would be the transitive property