Answer:
d. Milestones are developed during risk planning.
Explanation:
A milestone is a typical measuring point used when establishing cost control. Which of the following does NOT accurately describes the use of cost control milestones?Select one:a. Project managers and sponsors often decide the number of milestones jointly.b. Milestones are often identified in the project charter.c. Project managers can use their cash flow projections to determine the funding needed to reach each milestone.d. Milestones are developed during risk planning.
<u>ANSWER</u>
It is not correct that milestones are developed during risk planning but rather they are developed during Project budgeting where the deliverables are identified in terms of the cost to achieve them. Truly as stated in the scenario's options, Project managers can use their cash flow projections to determine the funding needed to reach each milestone. It is in the project planning phase that these milestones are established by Project managers and sponsors jointly.
Answer:
I think C is correct answer
The high and low levels of activity are 90,000 miles in April and 50,000 miles in February. The costs at these two levels are $195,000 and $120,000, re-spectively. The difference in costs is $75,000 ($195000-120000), and the difference in miles is 40,000 (90000-50000). Therefore, variable cost per unit is $1.875computed as follows.
75000÷40000=1.875
Determine the fixed costs by subtracting the total variable costs at either the high or the low activity level from the total cost at that activity level
Variable cost=1.875×50,000=93,750
fixed cost=120,000−93,750=26,250
Answer:
1.267 = Overhead Rate
Explanation:
<em>As general approach,</em> the manufacturing rate, along with any rate is done by dividing the cost by a cost driver.

In this case teh cost is the manufacturing overhead and the cost driver the direct materials cost:

<em>Using Direct Materials cost, the rate would be:</em>
