Answer:C. Simultaneous production and consumption.
Explanation:
Production and consumption occuring at the same time will not make products to differ.
Heterogenity which refers to different qualities in firms will lead to different products. Time perishable capacity which means idle time during low patronage will still allowed products differences, Abilities to limit the discretionary input of personnel will not debar product differences and Customer provides significant input into the process will allowed products differences.
Answer:
The answer is: Expected annual net cash savings are $16,750.
Explanation:
Please find the below for detailed explanations and calculations:
Payback period is defined as the time it takes an investment to recover its initial investment.
In this case, the initial investment is the cost of software package at $67,000, while the payback period is four years.
We apply the payback period formula to calculate payback period to calculate the Expected annual net cash savings:
Payback period = Initial investment / Net cash flow per period <=> Net cash flow per period = Initial investment / payback period = 67,000 / 4 = $16,750.
So, Net cash savings annually is expected at $16,750. In other words, if the firm is to save $16,750 per year from owning the software, it will take the firm 04 years to recover its initial investment.
Answer:
B
Explanation:
I think you've already figured this out for yourself, but I thought I'd answer anyway and maybe clarify some things.
Supply is the total amount of a <u>good or service</u> that is available to consumers.
- Think about it: goods are physical things bought and sold, like apples. Services are actions done for another person, like taxi driving or renting a used car.
- None of the other answers make sense: a "device" is not a strictly defined term in economics; an "industry" can't be available to consumers, and a "warranty" isn't applicable.
Answer:
Answer is the FCAC is greater than the TBC.
Refer below.
Explanation:
A second method for determining the forecasted cost at completion assumes that, regardless of the efficiency rate the project or work package has experienced in the past, the work to be performed on the remaining portion of the project or work package will be done according to budget. If the cumulative actual cost is greater than the cumulative earned value, then: FCAC is greater than the TBC.