Answer:
c. $90,700
Explanation:
The computation of the cost of the land is shown below:
= Purchase cost of land + property taxes + attorney fees + land graded cost
= $85,000 + $2,500 + $1,000 + $2,200
= $90,700
We added the property taxes, attorney fees, and the land graded cost to the purchase cost of the land. We do not include the parking lot expenses
Answer:
A
Explanation:
M2= 60+70+50+220+80= $480
hence option A is correct
MZM = $480-80+100= $500
Answer:
For such a report , the sql query required would be:
SELECT emp_id, curr_salary, curr_salary*1.03 AS inc_salary FROM Employee;
Explanation:
For such a report , the sql query required would be:
SELECT emp_id, curr_salary, curr_salary*1.03 AS inc_salary FROM Employee;
In the above sql query employee id is emp_id , curr_salary is the current salary column. "curr_salary*1.03" is been made because an increment of 3% means salary + salary*3% , that is , salary*1.03.
Answer:
Answer for the question:
A production line at VJ Sukumaran's machine shop has three stations. The first station can process a unit in 10 minutes. The second has two identical machines, each of which can process a unit in 12 minutes (each unit only needs to be processed one of the two machines). The third station can process a unit in 18 minutes.(This station operates separately from, and simultaneously with stations one and two, which are independent and sequential operations).
Which station is the bottleneck station?
is given in the attachment.
Explanation:
The activity's crash cost per time unit is $30.
Crash cost per time unit equals the cost slope.
Cost slope equals rise/run; therefore (crash cost - normal cost)/(normal time - crash time)
or ($160 - $100)/(8 - 6)
= $30.
Activity crash costs are the costs associated with choosing a faster alternative to do work. Note that this is the full cost associated with the alternative approach, not the added cost. Therefore, the formula returns a value representing the accident cost per period.
A project crash means adding additional resources to speed up the project completion time. Lowering normals can crash your project. Completion times for critical activities called activity crashes. This can be achieved by having more resources to run them.
Learn more about crash activity here:brainly.com/question/18349575
#SPJ4