Answer:
Explanation:
Run A Duration B Duration C Duration 1 51 48 17 2 60 48 19 3 30 39 19 4 31 48 22 5 30 31 14 6 41 16 17 7 44 12 6 8 44 12 10 9 45 43 9 10 60 41 10 Based on the simulated numbers given above, what is the average completion time of the whole project?
Since B is the predecessor of C.
Project completion time for each run will be calculated as Maximum (Duration of A, Duration of B +Duration of C).
Represent
Run = R
Duration of A = DA
Duration of B = DB
Duration of C = DC
Project Completion time = PT
<u>R DA DB DC PT</u>
1 51 48 17 48 + 17 = 65
2 60 48 19 48 + 19 = 67
4 31 48 22 48 + 22 = 70
5 30 31 14 31 + 14 = 45
6 41 16 17 41
7 44 12 6 44
8 44 12 10 44
9 45 43 9 43 + 9 = 52
10 60 41 10 60
<u> Total = 546</u>
Total Project completion time in 10 Stimulations = 546
Average project Completion time = 546/10 = 54.6
Therefore, average Project completion time is between 53 and 56 days.
The land ordinance of 1785 was the law that organized a way to divide and sell the land in the northwest territory. This law was the Ordinance of 1784 which was the resolution written by Thomas Jefferson who aims at the congress in order to call for an action. The law wants to fathom the mode of locating and disposing the lands in western territories in order to be used in other purposes.
The answer to this question is Variable cost.
As the level of production increase , the total variable cost is increased and vice versa.
Examples of variable cost are the cost of sugar in condensed milk factory, the cost of leather in bag manufacturing, the cost of coffee beans in starbucks, etc.
Answer:
200 units
Explanation:
For computing the number of units produced each time we need to applied the economic order quantity formula which is shown below:

where,
Annual demand is 1,600 units
Ordering cost per order is $25
And, the carrying cost or holding cost per unit per year is $2
Now placing these values to the above formula
So, the economic order quantity is

= 200 units
Answer:
133 acres of sugar cane
and 300 of soybean provide a profit of $ 733,000
Explanation:
We setup the fromulas and use excel solver:
labor hours: 3 x sugar acres + 4 x soybean <= 1,600
profit = 1,000 x sugar acres + 2,000 soybean
with the restriction soybean <= 300
SOLVER
acres hours PROFIT
sugar cane 133 x 3 = 399 x 1,000 = 133,000
soybeans 300 x 4 = 1,200 x 2,000 =<u> 600,000 </u>
TOTAL 733,000