Answer:
$660,000
Explanation:
WACC = [wD * kD * (1 - t)] + [wE * kE]
WACC = [(0.77 / 1.77)*6.12%* (1 - 0.40)] + [(1 / 1.77)*11.61%]
WACC = 1.60% + 6.56%
WACC = 8.16%
Present value of annuity = Annuity*[1-(1+interest rate)^-time period]/rate
Present value of annuity = $1.67*[1-(1.08156745763)^-9]/0.0816
Present value of annuity = $1.67*6.206374532
Present value of annuity = $10.36 million
NPV = Present value of inflows - Present value of outflows
NPV = $10.36 million - $9.7 million
NPV = $660,000
Answer:
slow growth in buyer demand, weakly differentiated products among rival sellers.
Explanation:
There a number of causes that relate to the firms rivalry among its competitors.
1. Barriers to entry.
2. Bargaining power of the buyers.
3. Bargaining power of the suppliers.
4. Threat of substitutes.
5. Slow industry growth.
6. Lack of differentiation and switching costs.
7. Diverse competitors.
8. High strategic stakes.
Answer:
E. It may encourage a sense of entitlement among employees.
Explanation:
Above the market, compensation in the form of wage strategy in which the organizations initiates high salaries to the employees. High salaries are provided to the employees to attract them and to retain them in the team. This is done to maintain the caliber of the group and for the smooth flow among the team members.
Answer:
Buster Norton and the Bonds of San Francisco Opera Company
If Mr. Norton purchases three of these bonds today, in 10 years from today at maturity, he will receive:
= $6,000.
Explanation:
a) Data and Calculations:
Face value of each zero coupon bond purchased = $2,000
Number of bonds purchased by Norton = 3
Value of bond investments at maturity = $6,000 ($2,000 * 3)
Maturity period of the San Francisco Opera Company bonds = 10 years
Annual Yield to Maturity of similar bonds in the market = 12%
From an online financial calculator:
Present value of bonds = $1,932 (with each as $644 ($1,932/3))
N (# of periods) 10
I/Y (Interest per year) 12
PMT (Periodic Payment) 0
FV (Future Value) -6000
Results
PV = $1,931.84
Total Interest $4,068.16
Question:
Graded assignment(towards 15% Hw grade) Saved Help Save& Exit Submit Check my work Your landscaping company can lease a truck for $7,800 a year (paid at year-end) for 6 years. It can instead buy the truck for $38,000. The truck will be valueless after 6 years. The interest rate your company can earn on its funds is 7%. 10 points
What is the present value of the cost of leasing?
Answer:
Cost of lease = $37,179.01
Explanation:
Leasing is a finance arrangement where one party (the lessor) transfers the right to use an asset to another party (the leasse) in exchange for a rent.
The cost of a lease to the leasee is the present value of the future lease payment discounted at the cost of capital.
So using the present value of annuity formula, we can work out the cost of the lease arrangement as follow:
PV =A× (1- 1+r)^(-n)/r
PV- Present Value
r- interest rate
n- number of years
A- annual lease payment
PV -
A-7,800
r-7%
n-6
PV = 7,800× (1- (1.07)^(-6)/0.07 = 37,179.01
Present Value = $37,179.01
Cost of lease = $37,179.01