Answer:
The slope of the CML = (13% - 7%)/25% = 0.24
Explanation:
Given that:
expected rate of return of 17%
standard deviation of 27%.
The T-bill rate is 7%.
You estimate that a passive portfolio invested to mimic the S&P 500 stock index yields an expected rate of return of 13% with a standard deviation of 25%.
The slope of the CML is
Slope of the CML = (Expected return of Market - Risk free return)/Standard deviation of market
The slope of the CML = (13% - 7%)/25% = 0.24
= (0.13 - 0.07) /0.25
= 0.24
Answer:
Logical order, activity duration, resource availability, imposed dates, and cash flow are the five factors that may slow down the completion of a project.
Explanation:
- The order in which activities should be completed is known as logical order. You wouldn't put down new carpet before removing the old one. As a result, the logical order is for the predecessor activity to come first, followed by the successor activity.
- The total number of work periods required to complete a scheduled activity (excluding holidays and other nonwork periods) is known as activity duration. By identifying the right people for the job and discussing the time frame of each activity with them, you can figure out how long each activity should take.
- The availability of resources, such as workers, to complete a project is referred to as resource availability. Obtaining commitments for equipment and workers in a project prevents days of no work from occurring. It is necessary to stick to a strict schedule.
- Imposed dates are deadlines for completing specific parts of a project. Perhaps your permit is only valid for 30 days. If this is the case, you must complete your project within the specified time frame. This date was not chosen; it was imposed by the permit.
- The term "cash flow" refers to the money that comes in from the financial backer as well as the money that goes out to the employees and subcontractors. If there is a cash flow problem on either end of the transaction, it can affect the entire project. Workers will not continue to work if they are not paid on time, and a project may be abandoned.
Source:
- Describe the five factors that may limit how fast a project can be completed. Give an example of each (Course Hero).
Answer: 1. B. Petty Cash
2. D. Petty Cash
3. D. Debit petty cash and credit cash
Explanation:
1. When creating the Petty Cash fund, Cash is credited because money is being removed from it. It is then put into the Petty Cash account hence a debit.
2. When taking money from Petty Cash, it is an asset and so is credited to reflect the outflow.
3. Similar to the transaction in question 1. You are taking money from cash account to.put in Petty Cash so the right procedure is to debit Petty Cash and credit Cash.
Answer:
$50
Explanation:
If the required reserves are 5%, then the money multiplier = 1 / 5% = 20. If the FED wants to increase the money supply by $1,000, then it needs to initially inject $1,000 / 20 = $50 into the economy.
When the FED wants to increase the money supply, it engages in an expansionary monetary policy. If it wants to decrease the money supply, then it will engage in a contractionary monetary policy.
75,000$
fgfffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffff