A CBA , used to justify the project is typically prepared in the analysis phase of the secsdlc, must be reviewed and verified prior to the development of the project plan.
A project plan is a collection of official documents outlining the project's execution and control phases. In addition to addressing scope, cost, and schedule baselines, the plan takes risk management, resource management, and communications into account.
A project plan is a document that outlines each step needed to complete a project from A to B. It is sometimes portrayed as a Gantt chart. It acts as a roadmap by outlining the project phases, important project tasks, their start and end dates, interdependencies, and project milestones.
Learn more about project plan here
brainly.com/question/15410378
#SPJ4
Answer:
Perfectly inelastic
Explanation:
A demand is perfectly inelastic when quantity demanded does not change in response to a change in price.
Answer: $35,000
Explanation:
Implicit rental price = Interest payment + Depreciation
Interest payment = 5% * 500,000
= $25,000
Implicit rental price is therefore:
= 25,000 + 10,000
= $35,000
Answer:
The correct answer is letter "D": Payment poster.
Explanation:
Payment posters are employees in charge of handling the payment systems for medical assistance. Among their duties, payment posters process payments for patients whether in cash or electronically and must have a wide knowledge of how insurances work in regards to benefits and refund requests.
We are given
fixed cost, F = $6,660,000
sales mix:
65% sporting goods
35% sports gear
margin ratio:
30% sporting goods
50% sports gear
Now, we solve for the break even point in dollars. We use the formula
x = total fixed cost / [ price - total variable cost/price ]
Using the given values
x = 6660000 / [0.65(0.3)(6660000) + .35(0.5)(660000)]/ [(0.3)(6660000) + (0.5)(660000)]
x = $14,400,000
The breakeven point is $14,400,000
This is the sales when the revenue is just equal to the total cost of producing the products resulting to zero profit.