Choosing a song that has recently been made is not a typical criterion for a good song to teach preschool children. This is because the type of songs that are used to teach them, are songs that have always been popular, whether they are from a known or unknown source, so they go through generations and teach the children traditions and knowledge that is part of the education system.
Answer:
C. the hindsight bias
Explanation:
the hindsight bias refers to people tendencies to see an situation that they already seen before as predictable. They will assume that the outcome will be pretty much the same as what they've experienced before.
From the excerpt above, we can see that Alexandra and Belinda the research that they read as 'the truth' without even conducting further investigation.
This most likely happened because both of them already has a pre-conceived notion regarding cosmetic surgery.
Alexandra always believe that cosmetic surgery can increase self-esteem while Belinda has always believed that cosmetic surgery cannot increase self-esteem even before they read the research. Both of them only treat the research as a small confirmation for the bias that they already held.
Its where a worker a<span>grees not to remain in or join a union</span>
The answer to this question is 15%.
This amount of depression rate is directly correlated with boththe amount of workloads required to pass the semester (including tests and homework) and the pressure to socially adapt and accepted by their peers within their social environments.
The earliest start time rule "compares the finish times for all immediate predecessors of an activity".
<u>Option: B</u>
<u>Explanation:</u>
The equation used only to measure Early Start and Early Finish dates:
Early Start of Operation = Predecessor Early Finish operation + 1.
Early Activity End = Period of Activity + Early Activity Start - 1.
The above given terms are basically dependent on how early a project or an operation may start by having all necessary element like how early a task can be started in given time duration. In same how early a work can be finished in business or another sector with in a given time duration. This helps to calculate a millage of a work performed.