<span>The journal entry to record the initial write-off includes is allowance for doubtful accounts. Allowance for doubtful accounts is a contra account to accounts receivable, and therefore has debit balance. It also needs to be diminished because you already used the bad debt when you make the allowance.</span>
Answer:
A. planning, scheduling, and controlling.
Explanation:
The phases of project management are -
1. Initiation
2. Planning
3. Execution - Scheduling
4. Control
5. Close
Option A is correct because the answer includes the 2nd, 3rd, and fourth phases of project management.
Option B is wrong because programming is not a phase of project management. Option C is a combination of management functions. Therefore, it is incorrect. Option D is not correct as the service project is not different from the manufacturing project. Option E is the project management technique.