Answer:
- Project A and C given a budgetary constraint of $15,000.
- Pick all projects if there was not constraint as they all have positive NPVs.
Explanation:
Find the NPVs of the various projects.
Project A:
= Present value of inflows - Cost
= 4,000 / 1.085 + 4,000 / 1.085² + 4,000 / 1.085³ - 7,500
= $2,716.09
Project B:
= 3,000 / 1.085 + 4,000 / 1.085² + 3,000 / 1.085³ - 8,000
= $511.52
Project C:
= 2,500 / 1.085² - 2,000
= $123.64
Seeing as she has only $15,000 to embark on projects, she should pick projects A and C.
Project A should be picked because it has the highest NPV and Project C should be picked because it can still be invested in after Project A given budgetary constraints.
Specialization benefits buyers and sellers. Focusing on a limited number of related products or services allows them to use capital and labor more efficiently.So , buyers get better products at lower price and sellers sell more products and they manufacture more products at lower costs.
Credit terms are specific repayment conditions as to how long customers have to pay bills and the amount of cash discount allowed.
<h3>What is the purpose of credit terms?</h3>
Credit terms are the payment requirements stated on an invoice. It is fairly common for sellers to offer early payment terms to their customers in order to accelerate the flow of inbound cash.
Credit means a loan, an agreement in which the lender (creditor) supplies the borrower with money, goods or services which is to be returned in future. Terms of credit apart from the rate of interest, collateral also includes documentation, mode of repayment.
To learn more about credit terms visit the link
brainly.com/question/13019978
#SPJ4
Answer:
understand
Explanation:
by understanding each other and work inline with the business goal in order to achieve the business objective