Answer:
Alternative A= $1570
Explanation:
Giving the following information:
It has three choices:
(a) Refurbish the old equipment for $800.
Materials and labor= $1.10 per board.
(b) make major modifications for $1,100
Materials and labor= $0.70.
(c) purchase new equipment at a net cost of $1,800.
Variable costs= $0.40.
Q= 700
Alternative A= 800+1.10*700= $1570
Alternative B= 1100+0.70*700= $1590
Alternative C= 1800+0.40*700= $2080
The cheapest alternative is Alternative A. To make a full analysis you need the selling price, which we don't have.
Answer:
D maybe the correct answer
More details please or actually ask the question.
<h2>Jamie's lack of motivation stems from a breakdown in the
Performance reward relationship.</h2>
Explanation:
It is the level of performance of employee that the employee feels and based on the performance, the employee expect promotion and increment.
Here in this situation, based on the self-evaluation of the promotion of Jamie, he would have expected the promotion but since it has been given to other manager, it has broken down the performance reward relationship of Jamie.
Promotion should be based on performance than considering other things which would help employer or manager to keep up the Performance reward relationship