Answer: $19037
Explanation:
The following can be deduced from the question:
Balance per Bank statement = $18361
Add: Deposits in Transit = $1450
Add: Bank error = $63
Less: Outstanding check = $837
Adjusted cash Balance per Bank:
= ($18361 + $1450 + $63) - $837
= $19874 - $837
= $19037
The adjusted cash balance per the bank records should be $19037.
N.B: The bank error was gotten as the difference between $92 and $29. $92 - $29 = $63
Answer:
Explanation:
X - number of units sold
Total cost for production = 1,500,000 + 1600X
Total cost for purchasing = 2000X
a. For 4000 units sold
Total cost for production = 1,500,000 + 1600 * 4000 = $7,900,000
Total cost for purchasing = 2000* 4000 = $8,000,000
In this case producing is cheaper. Therefore, it is better to produce
b. Y - break-even point
Then : 1,500,000 + 1600 * Y = 2000* Y
So 1,500,000 = 400 Y
Y = 3750
At №of units less than 3750 purchasing will be the better option
And above 3750 producing will be the better option
Answer: Because private companies will have difficulty getting anybody to pay for them.
Explanation:
Private markets fail to provide the optimal amount of some good such as public firework displays because private companies will have difficulty getting anybody to pay for them.
The main motive behind private markets are simply for making of profit but for public, the main motive is for the government to satisfy the needs to the people. Hence, with regards to the question, the answer will be that there'll be difficulties encountered in getting people to pay for the goods.
Price ceilings are the limit of the prices to go high above the given ceiling while the price floor limit the prices to go below the given amount. The two restrict the free exchange of prices by putting a range of prices allowable only for a certain product. The prices are already limited between the price floor and the price ceiling.
Answer:
Applet's flexible budget variance for total costs is $5,140 unfavorable variance since actual is higher than budgeted cost
Explanation:
Flexible budget variance for total costs=actual total costs-budgeted total costs of 72 connectors
actual total costs of 72 connectors=$19,000
budgeted total costs of 72 connectors=budgeted fixed cost+budgeted total variable cost of 72 connectors
total budgeted variable cost=72*$130=$ 9,360.00
budgeted fixed cost is $4,500
Budgeted total costs of 72 connectors=$9,360.00+$4,500.00=$ 13,860.00
Flexible budget variance =$ 13,860.00-$19,000.00=$5140 unfavorable variance