We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
Where is the diagram?
Step-by-step explanation:
Where is the diagram?
Answer:
<u>The correct answer is 2. a = 1/2, b = - 3, c = -2</u>
Step-by-step explanation:
1. Let's review the information provided for an answering the question correctly:
0 =1/2x^2- 3x- 2
0 = 1/2x² - 3x - 2
2. Let's find the values for a, b and c.
According to the quadratic equation, we have:
a = 1/2
b = - 3
c = - 2
<u>The correct answer is 2. a = 1/2, b = - 3, c = -2</u>
Answer:
10 - 3x
Step-by-step explanation:
Since the number 10 is decreased by 3x, that would mean the expression is 10 - 3x.
Hope this helped!
Answer:
- D. Neither
- x- intercept: (-13/6, 0), y- intercept: (0, 13)
- (-1, 3)
Step-by-step explanation:
#1
<u>Substitute pairs of solutions and verify</u>
(1, 7)
(2, -7)
- -7 = -2*2 - 5
- -7 = -11
- Wrong
Correct choice is <u>D. Neither</u>
#2
<u>x- intercept: y = 0</u>
- 6x + 13 = 0
- 6x = -13
- x = -13/6
- (-13/6, 0)
<u>y- intercept: x = 0</u>
- y = 6*0 + 13
- y = 13
- (0, 13)
#3
<u>x = -1 ⇒ find y:</u>
- y - 3 = 2(-1 + 1)
- y = 3
- (-1, 3)