SIZIF [17.4K]
4 years ago
5

Generate a plan and describe the steps needed to solve the equation. 34 = –(m + 3)

Mathematics
2 answers:
never [62]4 years ago
7 0

Sample Response:

The negative sign outside the parentheses represents –1. Distribute the –1 to everything inside the parenthesis. Use the addition property of equality first to add 3 to both sides. Then use the division property of equality to divide both sides by -1.

Goryan [66]4 years ago
4 0
You can rewrite it to this so it looks less complicated if you know the distributive property. 34 = -1(m+3) so then is becomes 34 = -m - 3 add 3 to both sides 37=-m m=-37
You might be interested in
Gavin needs $80 to buy a fish tank. He has saved $8 and plans to work as a babysitter to earn $9 per hour. Which inequality show
gavmur [86]

Answer:

<h2>n>8</h2>

Step-by-step explanation:

Step one:

given data

needed amount= $80

the amount already saved= $8

earnings per hour= $9

let the number of hours worked be n

and let y represent the total

the situation represented linearly is

y=mn+c

Step two:

substituting our data to find n

9n+8>80

9n>80-8

9n>72

divide both sides by 9

n>72/9

n>8

Therefore he must work a minimum of  8houees

4 0
3 years ago
3 (x+2) = 18<br> Can you please use the distributive property thx?
Black_prince [1.1K]

Answer:4

Step-by-step explanation:3x+6=18 minus 6 on both sides and divide by 3

5 0
3 years ago
45 people in a certain company can work together to finish a project in 15 days. For a project of the same workload, the
gayaneshka [121]

Answer:

45 days

Step-by-step explanation:

first Project using 45 workers, is finished in 15 days.

that is 15(45) = 675 worker•days of labor

second project is expected to take 675 worker•days of labor to complete as well

675 worker•days/ 15 workers = 45 days

5 0
3 years ago
Read 2 more answers
Can someone explain this to me and give me the answer to number 10?Thanks
AveGali [126]
You need to find area or what?
5 0
3 years ago
X^(2)+17x+72<br> im confused on how to factor this?
polet [3.4K]

Answer:

  (x +9)(x +8)

Step-by-step explanation:

In a quadratic with leading coefficient 1, the coefficient of the linear term (17) is the sum of factors of the constant term (72). If you know your times tables, you know that 8×9 = 72, and you also know that 8+9 = 17.

With these facts, you can write the factorization as ...

  (x +8)(x +9)

_____

If you need to see the working out, rather than jumping to the end, you can use the sum information to rewrite the linear term:

  x^2 +(8x +9x) +72

Now factor pairs of terms:

  (x^2 +8x) + (9x +72) = x(x +8) +9(x +8) = (x +9)(x +8)

_____

It also helps to be familiar with the product of binomials:

  (x +a)(x +b) = x^2 +(a+b)x +ab

4 0
3 years ago
Other questions:
  • I need help with number 6
    10·2 answers
  • I need help on this question
    8·1 answer
  • One number is seven less than five times another. If their sum is decreased by four the result is one. Find the numbers
    10·1 answer
  • If x=4 evaluate -x.
    13·2 answers
  • Can y’all help me with this please
    15·1 answer
  • Sarah deposits $500 into a bank account earning 2% interest per year. The amount
    14·2 answers
  • Lindsay ordered twice as many blankets as she did quilts for the department store where she works. The order was for 129 items.
    6·1 answer
  • What is irrational numbers and what is rational numbers?
    7·1 answer
  • What is the value for y in the following equation when x= 2?
    7·2 answers
  • is the table proportional
    14·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!