The word that completes the sentence that relates to the suppliers' profit maximized at equilibrium is demand. Demand is related to the consumer. At equilibrium, the supplier's profit is maximized at the same time the consumer's demands are optimized.
A data analyst of a construction company chooses to analyze the historical data as the construction project is for a very short time period.
<h3>
What is a construction company?</h3>
A construction company is an entity that takes on construction projects of making buildings, towers, bridges, flyovers, etc.
When the construction project is for a short duration, then the data analyst decides to analyze the historical data, that is, the data that is based on past figures and has not been affected by any market fluctuations. It helps the data analyst to make a report in a quick manner without any kind of further delay.
Therefore, the historical data can be studied by a data analyst where the construction project is completed in a short span of time.
Learn more about the data analyst in the related link:
brainly.com/question/26253705
#SPJ1
Answer:
The price of the bond will be $879
Explanation:
Price of the bond is the present value of all cash flows of the bond. Price of the bond is calculated by following formula:
According to given data
Coupon payment = C = $1,000 x 6.2 = $62 annually = $31 semiannually
Number of periods = n = 2 x 8 years = 16 periods
Current Yield = r = 8.3% / 2 = 4.15% semiannually
Price of the Bond = $31 x [ ( 1 - ( 1 + 4.15% )^-16 ) / 4.15% ] + [ $1,000 / ( 1 + 4.15% )^16 ]
Price of the Bond = $31 x [ ( 1 - ( 1 + 0.0415)^-16 ) / 0.0415 ] + [ $1,000 / ( 1 + 0.0415 )^16 ]
Price of the Bond = $31 x [ ( 1 - ( 1.0415)^-16 ) / 0.0415 ] + [ $1,000 / ( 1.0415 )^16 ]
Price of the Bond = $521.74 + $357.26 = $879
The correct answer is D) maintain a uniform level of required resources.
The start of noncritical activities is delayed beyond their earliest start times (but not beyond their latest start times) in order to maintain a uniform level of required resources.
That is why companies have to establish their priorities and identify the main activities that must be accomplished on time, the people responsible to accomplish the activity, and the resources needed to successfully do so. Noncritical activities can be delayed up to a point, but the critical activities have to be followed according to the schedule.