Answer:
B. Click Set Up, Slide Show, and then select the Loop continously until 'Esc' and use timings, if present options.
Explanation:
PowerPoint presentation is a program which was developed by Microsoft. It is a platform which is used to create business presentation or educational presentations, etc.
In order to play the slide show continuously without our interaction, we need to do the following steps :
1. In the powerpoint presentation, we have to click "Slide Show" tab in the ribbon and then click on the "Set up slide show" on the Set Up bar.
2. The set up slide show dialogue box will pop up. In this we have to check or tick on the "Loop continuously until 'Esc' " in the "Show Option" and then click 'OK'
3. Now in the "Slides" preview side panel, we have to click the 1st slide , then Press and hold the 'Shift' key and then click the last slide. This selects all the slides.
4. Now, in the transition tab, in the "Timing" group, we have or uncheck or untick the " On Mouse Click " and also check the " After"
Answer:
The correct answer is C) With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
Explanation:
The CPM (Critical Path Method) method is frequently used in the development and control of projects whose tasks have a fixed duration while the PERT (Program Evaluation and Review Techniques) method is a set of techniques with the same purpose but that allows to work with tasks with estimated probability duration but not deterministic.
Both methods are based on developing a complete scheme that includes all the tasks of a project linked to each other according to their sequence, determining the duration and analyzing different ways of reconfiguring the task planning to optimize the use of the resources of according to the general objectives of the project.
There are tasks that to start performing them must have been completed one or more previous tasks. The overall duration of the project is determined by the Critical Path, which is the sequence of tasks of greater duration. The tasks belonging to the critical path have to be carried out with special care because delays in them would cause delays in the total achievement of the project. That is why these tasks have no slack.
The rest of the tasks have some slack, which is determined by the time that a previous task can be delayed without delaying the total time of completion of the project, that is, not exceeding the duration determined by the critical path.
That is that why we say that the <em>slack</em><em> is the amount of time a task may be delayed without changing the overall project completion time</em>.
Answer:
O(n²)
Explanation:
The worse case time complexity of insertion sort using binary search for positioning of data would be O(n²).
This is due to the fact that there are quite a number of series of swapping operations that are needed to handle each insertion.
Answer:
Stereotyping
Explanation:
According to my research on information technology, I can say that based on the information provided within the question it can be said that your boss is exhibiting Stereotyping which could be inhibiting his creative problem-solving approach. Just like in psychology, stereotyping is over-generalized belief about a particular something. Which in this case since his boss saw a similarity in the problem with another problem he previously had, he automatically assumed he knew the cause and how to fix it.
I hope this answered your question. If you have any more questions feel free to ask away at Brainly.