Answer
The answer and procedures of the exercise are attached in the following archives.
Step-by-step explanation:
Gross profit = Sales - Cost of goods sold
= (440 x 90 + 220 x 80 + 264 x 50) - (440 x 56.7 + 220 x 50.4 + 264 x 31.5)
= (39,600 + 17,600 + 13,200) - (24,948 + 11,088 + 8,316)
= 70,400 - 44,352
= $26,048
Ending inventory schedule attached in the excel archive
You will find the procedures, formulas or necessary explanations in the archive attached below. If you have any question ask and I will aclare your doubts kindly.
Answer:a.Total manufacturing costs for Job 313 =$52,500
Unit Product Cost for Job 313=$30
Explanation:
Total manufacturing costs=Direct materials+Direct labor costs+Overhead costs
But Overhead cost =115% of direct labor cost
= 115% x $10,600
=$12,190
Total manufacturing costs =$29,710 + $10,600+$12,190
=$52,500
Unit Product Cost=Total Manufacturing costs/ Total Number of Units Produced =$52,500 /1,750 units
=$30
Answer:
Based solely on a difference of values between the counselor and the client.
Explanation:
Referral is defined as the situation were counselors make recommendations of where else a client might seek treatment. This can happen if counselors cannot accept the client for some reason or if the client's needs have changed. Something that must be said is that the reasons must be appropriate, and a difference in values is not.
Answer:
The correct answer is A that is late start date.
Explanation:
Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.
The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.
So, the late start date for the activity is the latest possible time.