Answer:
Marginal Revenue Product=150
Marginal Resource Cost= 100
Explanation:
Marginal revenue product (MRP) is the change in total revenue that results from a unit change of some type of variable input.
Marginal Revenue Product= Revenue Change
/Additional Input
Marginal resource cost (MRC) is the change in total cost that results from a unit change of some type of variable input.
Marginal Resource Cost= Cost Change
/Additional Input
In this situation we must calculate the change of revenues (MRP) and cost (MRC) when we add a new vehicle.
We are increasing our delivery fleet in 1 unit
First calculate the change in total revenue
Total revenue= 1,500 packages * $0.10 in revenue=150
Marginal Revenue Product=$150/1=150
The Cost change is $100,
so Marginal Resource Cost= $100/1=100
Yes, Rubio will be able to successfully sue and collect the $1,000 later because their agreement was not fulfilled.
<h3>What is an agreement in contract?</h3>
In contract, an agreement is an element of what makes a contract valid. When an agreement is breached, then, the aggrieved party have a right to void the contract.
In conclusion, the answer is yes because Rubio will be able to successfully sue and collect the $1,000 later because their agreement was not fulfilled.
Read more about agreement
<em>brainly.com/question/997952</em>
<u>Solution and Explanation:</u>
The given data is as follows:
Error rate = 4%, per hour payment of inspector = $8, inspection of units = at the rate of 49 per hour, cost = $9 per unit
The problem can be solved as considering an opportunity to have an improvement of 4% in the quality.
In case inspector is not hired then it will cost .04 multiply 9= $.3.6 per unit and in case the inspector is hired it will cost $ 0.163 approx.(8 divided by 49).
Therefore, on comparison, it is recommended to hire the inspector.
Answer:
The correct answer is $12,060.
Explanation:
According to the scenario, the given data are as follows:
Production in June = 400 units
Production in July = 410 units
Each unit required = 5 pounds
Cost per pound = $6
So, June required raw material = 400 units × 5 pounds = 2000 pounds
For July required raw material = 410 units × 5 pounds × 20% = 410 pounds
So, required total raw material for June = 2000 pounds + 410 pounds - 400 pounds ( already in inventory)
= 2010 pounds
So, the total cost required for raw material in June = 2010 pounds × $6
= $12,060
Hence, the budgeted cost of purchases for raw material K for June is $12,060.