Answer:
Please consider the following explanation
Explanation:
a. EOQ = 560 units
b. 58800 units/560 units = 105 orders
c. EOQ/2 = 560/2 = 280 units (average inventory)
d. 105 orders × $4 ordering cost = $ 420
280 units × $1.50 carrying cost per unit = 420
Total costs = $840
Answer: The correct option therefore is > upward sloping
Explanation:
When resources are limited in quantity, the cost of production would increase. Hence, in the long run, the supply curve will be upward sloping.
Answer: contingency
Explanation:
Contingency planning is a form of planning that is used by an organization in order to plan ahead in case an event occurs. Contingency plans can also be called a 'Plan B' due to the fact that it's an alternative action in case things does not go as planned.
Therefore, based on the question, Pinnacle is practicing contingency planning.
Answer:
I think you mean Patrick Jørgensen
Explanation:
He is a musical artist and if you don't mean Patrick Jørgensen I'm sorry