Answer and Explanation:
a. The computation of overhead rate using activity-based costing is shown below:-
Cutting = Cost ÷ Machine Hours
Cutting = $381,600 ÷ 228,000
= $1.67 Per Machine Hours
Design = Cost ÷ No. of Setup
Design = $620,100 ÷ 1,710
= $362.63 per set up
The computation of the amount of Overhead Allocated is shown below:-
Wool:
114,000 × $1.67
= $190,380
= 1,140 × $362.63
= $413,398
Total = $603,778
Cotton:
114,000 × $1.67
= $190,380
= 570 × $362.63
= $206,669
Total = $397,049
The computation of amount allocated using traditional approach is shown below:- = $1,001,700 ÷ 2
= $500,850
Overhead Allocated to Wool = $500,850
Cotton = $500,850
Answer:
A request fro proposals is the correct answer.
Explanation:
D. They can cause employees to lose their jobs unfairly.
Answer:
$3,735
Explanation:
The computation of the total cost that will be included in the numerator of that calculation is shown below:
= Beginning work in process + cost added during the period
= $350 + $3,385
= $3,735
Basically, we added the beginning work in process and the cost added during the period
The same amount is shown on the numerator side while calculating the cost per equivalent unit
Answer:
The correct answer to the given question is<u> “D – Short-Run Aggregate Supply Left”
</u>
Explanation:
While the problem is there for offering and deriving, less asset is being completed on the budget. Thus due to the lack of capital. The investment standard growing will decrease and therefore as an outcome, short run cumulative source curve will move to the left.