We can move the values of "n" and the numbers to their own sides:
22 = 8 + 2n
-2n = 8 - 22
-2n = -14
2n = 14
n = 7
Answer: Inactivity fee
Step-by-step explanation:
The rest of the options are not given but there can only be one correct answer to this question and that's the answer above.
Brokerages earn a return when they trade financial instruments for investors as they take a commission from this. When an investor has not traded for a while, brokerages don't get to make earnings and will be holding the account with minimal rewards.
To compensate for this, they charge an inactivity fee that will ensure that they get some form of earnings for managing the account and not receiving commission.
Answer:
Therefore 160 workers needed to build 16 miles of highway in 15 weeks.
Step-by-step explanation:
Given that,
the amount of time to build a highway varies inversely with the number of workers and varies directly with the length of the highway.
i.e
T= time, L= length of highway and W= number of workers.
So,we can rewrite the above equation
Here, = 100 worker, = 4 miles, = 15 weeks
= ?, = 16 miles, = 15 weeks
[ Multiply both sides]
Therefore to build 16 miles of highway in 15 weeks 160 workers needed.