The minimal completion time for the activities is the shortest possible time for all the activities to be finished. In doing this, we look at the path that would require the greatest amount of time. At the START node, we choose the path that would take the longest which is 7 days leading to ACTIVITY D. Next, we choose the path leading to ACTIVITY B which takes 5 days. Then, we move to ACTIVITY C taking 5 days and finally, reach the END which would take 6 days. So, the minimal completion time is:
7 + 5 + 5 + 6 = 23 days
Answer:
1. Melissa wants to check the accuracy of the finance charge on her promissory note. She has a $6,000, 4-year loan at an APR of 3.11%.
What is her monthly payment?
$133.10
Answer:
5 or -5
Step-by-step explanation:
The absolute value, or the distance of a number from zero has to equate to 5. This means that -5 or 5 can be the answer since -5 is 5 spaces from zero and 5 is 5 spaces from zero on a number line.
Answer:
r=10
Step-by-step explanation:
Take 4 away from 5 to isolate your variable. Now you have r/10= 1. figure out the unknown value by placing ten on top which is the same as 1.