1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
marysya [2.9K]
4 years ago
12

{3x+4y=36 {y=-1/2+8 Solve this system of equations

Mathematics
1 answer:
NemiM [27]4 years ago
4 0

Answer:

Step-by-step explanation:

What up you got scammed

You might be interested in
Multiply the complex numbers: (3 + 2i)(3 - 2i)
stealth61 [152]

Answer: 13

Step-by-step explanation:

Multiply 3*3 get 9

Multiply 2*2 get 4

Add 9+4 and get 13

3 0
3 years ago
Read 2 more answers
How would i work this out?
Varvara68 [4.7K]
You want to find the number of visits IN BETWEEN 12:30 PM and 6:45 PM

there some visits already recorded before 12:30. These visits are visits that you want to exclude but are included in the TOTAL visits

Before 12:30 the website has 1200 visits and at 6:45 the website has 14000.

You can do 14000-1200 to find the number of visits in the time frame between 12:30 and 6:45

ANSWER 12800 visits

3 0
2 years ago
Which functions are increasing?
maria [59]
The two bottom functions are increasing.
Increasing means they are going in an upward direction from left to right.
7 0
3 years ago
Read 2 more answers
Farmer Joe has a rectangular pasture that is fenced in for his cattle. He bought some horses and wants to cut the pasture in hal
nexus9112 [7]
So he goes from side 2 to side 4 there is his cut have a nice day sir/maam

7 0
3 years ago
Read 2 more answers
The first bricklayer can build a wall in 15 days, the second bricklayer can build the same wall in 20 days. How long will it tak
Ugo [173]

Answer:

It takes <u>8  4/7 </u>days for both bricklayers to build the wall together.

Step-by-step explanation:  

The first bricklayer takes 15 days to build the wall, which means it builds 1/15 of the wall per day.

The second bricklayer takes 20 days to build the wall, which means it builds 1/20 of the wall per day.

So if they build the wall together, the expression below will tell how much of the wall they build per day together.

1/15 + 1/20

To add the fractions, we must find a common denominator, which is 60.  

4/60 + 3/60, which equals 7/60.

So, they can build 7/60 of the wall per day together.  How many days will it take them?  We must find how many times 7 fits into 60, which can be done by solving 60/7, which is 8 4/7.  

So, it takes 8 4/7 days for both bricklayers to build the wall together.

7 0
3 years ago
Other questions:
  • What is the first step needed to solve 3 over 4 the whole multiplied by x minus 3 equal negative 18? Add 3 to both sides Subtrac
    15·2 answers
  • Devise the exponential growth function that fits the given data, then answer to accompanying question. Be sure to identify the r
    11·1 answer
  • How many square feet of outdoor carpet will we need for this hole
    8·1 answer
  • Question: -3x – 10 = 32
    11·2 answers
  • it rained 4/5 on monday. on Tuesday it rained 7/10 inches less than on monday. How much did it rain on tuesday​
    9·1 answer
  • In the given triangle,
    8·2 answers
  • Simplify the expression:<br><br> 3x2 - x + 7 + 5x + 2 - 2x2
    13·2 answers
  • If 2 &gt; -a, then _____
    5·1 answer
  • Help plsssssssssssssss
    13·1 answer
  • 6 erasers cost $6.60.<br> Which equation would help determine the cost of 3 erasers? Choose 1 answer
    10·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!