1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
s2008m [1.1K]
4 years ago
14

HELP MATH!

Mathematics
1 answer:
Darya [45]4 years ago
6 0

Answer:

theres 1 set of 3

Step-by-step explanation:

You might be interested in
A silo is in the shape of a cone. The silo is
dimaraw [331]
We need to find the volume of the cone to first see how much total wheat we can fill. So,
V=(pi)r^2(h/3) 
V=(pi)2^2(9/3)
V=(pi)4(3)
V=(pi)(12)
V=37.7 meters cubed.

If 1 cubic meter is equal to $232, we simply take the volume (37.7) and multiply that by the cost of 1 cubic meter ($232).

232x37.7= 8,746.40

----- It will cost $8,746.40 to fill up the silo with wheat -----


5 0
3 years ago
How many times does three go into 35 m
puteri [66]

\huge\boxed{11\;times.}

We have the question...

How many times does 3 go into 35?

Well, this is pretty simple all you have to do is count up by 3s until you get to the number. Remember, it doesn't have to be exact though. So, here we go count by threes 11 times. We get 33 from 3*11. Therefore, your answer will be 11 times.

6 0
3 years ago
Read 2 more answers
A point in the figure is selected at random. Find the probability that the point will be in the part that is not shaded
Mariulka [41]
I believe the answer is 25% or C). If you flip the half circles around then you get a full circle. When you look at the corners it is about 25%
4 0
3 years ago
Read 2 more answers
Urgent Math Help Needed ASAP
Marta_Voda [28]

Answer:

Fourth option: 30 days

Step-by-step explanation:

We three path to complete the project:

Path A:

A1 → A2 → A3

10 days → 8 days → 9 days = 27 days


Path B:

B1 → B2 → B3

2 days → 7 days → 3 days = 12 days


Path C:

C1 → C2 → C3

10 days → 8 days → 12 days = 30 days


Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished

7 0
4 years ago
Which of the following statements accurately describes the result of an increasing worker-per-beneficiary ratio in the Social Se
Nat2105 [25]
B is the answer fs no doubt
4 0
3 years ago
Other questions:
  • Your mom opens an account to save money for a family vacation. The account earns an annual interest rate of 4%. She earns $37 in
    14·2 answers
  • Carl earns $9.25 per hour. He worked 4.75 hours Monday, 2 5/8 hours Tuesday, and 7/2 hours Wednesday for three straight weeks. H
    7·1 answer
  • Factor: x(y − 1) + y(y − 1)
    7·1 answer
  • Simplify: (–4) • (9) – (5) • (–2) <br> A)2 <br> B)–36 <br> C)–26 <br> D)82
    13·1 answer
  • The angle of elevation to the top of a water tower from point A on the ground is 19.9°. From point B, 50.0 feet closer to the to
    12·1 answer
  • Determine if the function is linear. if it is, find the rate of change
    5·1 answer
  • A band charges $600 for 90 minutes. How much would they charge for two hours? with explanation
    15·1 answer
  • I need help on these three PLEASE!!
    10·2 answers
  • Points just solve 2 + 3 &lt;3
    11·2 answers
  • Solve the equation for x. <br><br> x + 13 = 22​
    12·2 answers
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!