The first one is the correct one
Answer:
Integrated change control
Explanation:
Integrated change control is a process in project management that involves managing all changes that may occur during the project.
It involves<u> reviewing the requests for change</u> from different areas of the organization, and <u>deciding whether to accept or reject these requests.</u>
Change requests may include; <em>changes to the budget, processes, project timeline or the project plan.</em>
If a request for change is accepted, then it's implementation must be monitored and controlled.