Answer:
Minimum cycle time = time for longest task = 2.4 minutes
Maximum cycle time = sum of the times to complete all the tasks = 18 minutes
Step-by-step explanation:
For the minimum cycle time, the reasoning is that all the tasks can be done simultaneously, at some during the assembling task. Hence, minimum time to complete one cycle is the time it takes to complete task that takes the longest time to complete.
For the maximum cycle time, the reasoning here is that each task is done after the completion of the previous task. The total time taken to finish the task will then be the sum of the time taken to complete each task. This usually is at the beginning of operations.
Answer:
x < - 2
Step-by-step explanation:
given - 4.9x + 1.3 > 11.1 ( subtract 1.3 from both sides )
- 4.9x > 9.8 ( divide both sides by - 4.9 )
Remembering to reverse the direction of the inequality symbol as a result of dividing by a negative quantity.
x < - 2 ← inequality reversed
solution set : x ∈ ( - ∞, - 2 )
Answer:
i really like your oroile pic sorry for bothering you
Step-by-step explanation:
<span>the line over the 28 means the 28 repeats forever.
1.282828.... and so on
let x be the rational number 1.28...
we can use this trick:
100*1.282828....= 128.282828... (the decimal 28 part repeats)
100x = 128.28...
next:
100x - x = 128.282828... - 1.282828...
the .282828... part will be subtracted away
99x = 127
divide both sides by 99 to get
x= 127/99</span>