Go to a blank cell and type
=AVERAGE(A1:A10) then <ENTER>
As if by magic, the average of those cells
will appear where you typed the formula.
Answer:
There are multiple critical paths
Explanation:
The critical path method (CPM), or critical path analysis (CPA), is an algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique (PERT). A critical path is determined by identifying the longest stretch of dependent activities and measuring the time required to complete them from start to finish.
The essential technique for using CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (typically categorized within a work breakdown structure),
- The time (duration) that each activity will take to complete,
- The dependencies between the activities and,
- Logical end points such as milestones or deliverable items.
Using these values, CPM calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer. This process determines which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer).
considering the above function of the cpm analysis because you have multiple path, there is tendency that more than path through the project network will have zero slack values.
The most significant difference between improving an existing process and designing a new process is that as a person is completely working again on a process or designing a new process, there are known to be a lot of unknowns factors that may occur.
<h3>What is the difference about?</h3>
In working or redoing a process or designing any kind of new process, there are known to be a lot of unknowns factors.
This is said to be the most significant difference that exist between improving a process and designing a new process. This makes a lot of new processes and products to be very focus on meeting their customer's performance needs or aims.
Learn more about designing from
brainly.com/question/1212088
#SPJ1
<span>Not a valid IPv6 address
A valid IPv6 address consist of 8 groups of 4 hexadecimal numbers separated by colons ":". But that can make for a rather long address of 39 characters. So you're allowed to abbreviate an IPv6 address by getting rid of superfluous zeros. The superfluous zeros are leading zeros in each group of 4 digits, but you have to leave at least one digit in each group. The final elimination of 1 or more groups of all zeros is to use a double colon "::" to replace one or more groups of all zeros. But you can only do that once. Otherwise, it results in an ambiguous IP address. For the example of 2001:1d5::30a::1, there are two such omissions, meaning that the address can be any of
2001:1d5:0:30a:0:0:0:1
2001:1d5:0:0:30a:0:0:1
2001:1d5:0:0:0:30a:0:1
And since you can't determine which it is, it's not a valid IP address.</span>
Answer:
Excel MIN Function
Explanation:
Excel MIN Function is used to get the smallest value which means, it returns the smallest value in the array(a set of data).
syntax is =MIN (number1, [number2], ...)